Thursday 9 July 2015

URWSS PROJECT : A FLAG BEARER OF THE SWAp : A Case Study


ABSTRACT

2.1 The pilot phase of the Rural Water Supply and Sanitation Project of Uttar Pradesh inclusive of Uttarakhand (Popularly known as Swajal Project) implemented during 1996-2003, became a sector model in India. Demonstrated success of the Swajal Pilot Project encouraged the Government of Uttarakhand decided to scale it up for improved coverage in the State, adopting a sector-wide approach. The scaling up project, now termed as ‘Uttarakhand Rural Water Supply and Sanitation Project’ ( ‘Global First’ RWSS Project), is unique on several counts. Concepts such as decentralization, partnership, community management, effective demand, gender analysis and cost recovery are deeply engrained in the project principles adhering to the 73rd constitutional amendment of the Indian constitution.

2.2 The project covers entire rural areas of the Uttarakhand State. The project is facilitated by the Department of Drinking Water, GoUK and executed by three agencies namely Uttarakhand Peyjal Nigam (UJN), Uttarakhand Jal Sansthan (UJS) and Project Management Unit (Swajal). International Development Association (IDA)-World Bank, Government of India (GoI), Government of Uttarakhand (GoUK) and Rural Beneficiary Communities jointly fund the project. The project has a total budget of $ 224 million of which the IDA credit is limited to a maximum of $ 120 million. The Project commenced its operations in November 2006. The project end date is June, 2012.

2.3 The case study attempts to: (i) describe the project in brief. (ii) identify some unique characteristics of the project. (iii) share experiences and good practices under the project, including their applicability and efficacy in improving sustainable service for the rural communities and. (iv) lessons learnt for better working and planning with communities.

3. INTRODUCTION

3.1 The delivery of sustainable rural water supply and sanitation service is an issue of considerable concern among policy planners and water sector managers of the country. The case study is intended for managers and planners who are concerned with the challenging problem of how to deliver sustainable water supply and sanitation services in the rural areas. Evidence exists to support that sustainable delivery of water supply and sanitation services encompasses not only technical issues, but also managerial, social, financial and institutional issues.

3.2 The current project design is such that it moves away from target based, supply driven model to a demand based approach where users get the service they want and are willing to pay for across the rural area of the state, i.e., across the sector . The basic principles for reform in the RWSS sector include community participation in the planning, implementation, operation, and maintenance (O&M) for the schemes of its choice, and the changing role of the government from that of a service provider to a facilitator.

3.3 The unique features of the project have benefited / are benefiting rural communities in several ways. Admittedly, the culture of dependence on outsiders for a basic necessity like water supply has been considerably reduced by the empowered User Water and Sanitation Committee (UWSSC) as regards to quality, quantity, service level and system reliability of the water supply scheme. The benefits accrued to communities due to sustainable operation and maintenance of water supply scheme by the VWSC include (i) reduction in coping cost as well as more availability of house hold space due to elimination of storing water in larger containers (ii) elimination of travel time and travel cost in lodging no-water complaints, making payment of bills/getting corrections in wrong bills and getting sanction of new water connection (iii) improvement in Mean Time Between Failure (MTBF) due to better quality of repairs and strict control/supervision by the community and (iv) most importantly, reduced bureaucracy.

4. BACKGROUND
            
4.1 The water scarcity in hilly region is a major issue being faced by the state Data from existing water supply schemes indicated that nearly 30 percent of the schemes suffered from a decrease in the availability of water, especially during the summer months, because of depletion of water sources. This also caused some of the villagers to spend considerable amount of time collecting water for domestic use, averaging one to three hours per day; even more time is spent in hilly locations. The problem was aggravated by water supply systems which had outlived their design life, and inadequate O&M.

4.2 It is widely recognized that supply driven rural water supply and sanitation (RWSS) service delivery does not adequately serve the requirements of user communities as they are often located at sites without consideration of community needs or preference. Planning of RWSS services also takes place without due attention to resource availability or quality, and the schemes are rarely financially viable. The end result is a government-dominated and target-driven service that has become unsustainable.

4.3 The current project significantly differs from previous efforts to supply water. The tenets of the current project include the following (i) a community led participatory program which aimed to provide drinking water facilities in rural areas with minimum provision of 40 lpcd (ii) adoption of a demand-responsive, adaptable approach along with community participation based on empowerment of villagers to ensure their full participation in the project through a decision making role in the choice of the drinking water scheme, planning, design, implementation, control of finances and management arrangements; (iii) full ownership of drinking water assets with Users Water and Sanitation Committee; (iv) communities to have the powers to plan, implement, operate, maintain and manage all water supply and sanitation schemes, (v) partial capital cost sharing either in cash or kind including labour or both, 100% responsibility of operation and maintenance (O&M) by the users; (vi) an integrated service delivery mechanism; (vii) taking up of conservation measures through rain water harvesting and ground water recharge systems for sustained drinking water supply; and (viii) shifting the role of Government from direct service delivery to that of planning, policy formulation, monitoring and evaluation, and partial financial support.

5.  OBJECTIVES AND STRATEGIES

5.1 OBJECTIVES :

The project’s development objective is to improve the effectiveness of RWSS services through decentralization and increased role of PRIs and involvement of local communities in the state of Uttaranchal. The project is also expected to bring associated benefits, including improved health resulting from reduced water-borne diseases, environmental sustainability through protection and management of water source catchment areas, time savings in fetching water would enhance the rural population, especially women. The project envisages upgrading no or partial coverage of water supply to full coverage with sustainable service, benefiting at least 1.2 million people, or 20% of the rural population. The project will also improve sanitation in about 30% of rural communities, to be declared free of open defecation.

5.2 STRATEGIES:

5.2.1 Policy Decisions- Recognizing the need for scaling up reforms, the GoUK issued its RWSS sector policy. The key elements of the policy included: (i) decentralized service delivery through devolution of administrative, executive, and financial powers to the three-tier PRI institutions; (ii) establishment of the SWSM and DWSMs, to oversee the policy and planning for the sector; and (iii) adoption of the integrated approach to service delivery, linking water supply, sanitation, health and hygiene, catchment-area conservation, and community-development initiatives.

5.2.2  Pro activeness of Top political leadership and committed bureaucracy, willingness to implement reforms at the senior level and a broad consensus of priorities created momentum and legitimacy to drive SWAp Program. The progress of SWAp has been made an integral part of Annual Confidential Reports.
5.2.3 Introduction of uniform computerized accounting system: It was recognised that the timely reimbursement of project cost is dependent on timely preparation of consolidated financial statement. Therefore, a computerized accounting system having ‘account code classification system’ was operationalized in the all the implementing agencies offices.
 5.2.4 Adequate Change Management:  Appropriate change management efforts to shift the mindset of the sector institutions from service provider to a facilitator were whole-heartedly taken up by engaging reputed training institutes.
5.2.5 Manuals such as Operations Manual, Procurement Manual, Financial Management Manual and Technical Manual for implementation of the project were prepared and agreed with the World Bank before embarking on actual implementation.
5.2.6 Information, Education, and Communications (IEC): The project printed booklets, leaflets, and posters that provided messages on the project, including use of toilets, health and hygiene aspects, A documentary film depicting detailed processes for implementation of the project was prepared.

6. DESCRIPTION OF THE WATER SUPPLY SCHEME:

The case study does not highlight the case of a particular water supply scheme but dwells on essential features of the URWSS project as a whole. The implementation of the project is being done by adopting following strategies etc.

6.1   RESOURCES :

6.1.1 RWSS Institutions: The execution of program is envisaged through three line agencies (Project Management Unit Swajal, Uttarakhand Jal Sansthan (UJS) and Uttarakhand Peyjal Nigam (UJN)). SWSM and DWSM are constituted towards overseeing the activities of three line agencies at the State and district level. All decisions for planning, design, implementation and maintenance are decentralized at the district and village level. The village User Water & Sanitation Committee (UWSSC) under the Gram Panchayat is fully responsible for the intra-village scheme design, procurement, implementation and management. UJS and UJN are responsible for bulk water supply under multi-village schemes.    

6.1.2 Community Development Support: The Support Organizations (SOs) are contracted for community development and technical support to the UWSSCs.  The SO is contracted by district implementing agency, based on a district specific short list of applicants, as per procurement guidelines.

6.1.3 Community Mobilization: The project puts up efforts at mobilizing households for group action through the UWSSC, a sub-committee of the GP. The composition of the UWSSC is interesting as the rural women constitute 30%, with an equally good number from Scheduled Caste and Scheduled Tribe households. Communities have shown tremendous interest and enthusiasm in shouldering responsibilities, including procurement and financial management activities. 

6.1.4 Financial Resource : The total water sector investment committed is $224 million for the SWAp. Partners for the SWAp pool ($224 million) include Government of India (31%), Government of Uttarakhand (67%); and the User Communities (3%) financial share. The International Development Agency will reimburse the Government of Uttarakhand share of SWAp basket up to $120 Million, against an annually varying reimbursement pattern, agreed in the PAD. The three sub-components and percentage share by GoUK is given below.

Table 1- Component wise SWAp Budget- share of GoUK

SWAp Program Components

Total Budget
GoU share
% IDA Reimbursement


Million $
%
A
RWSS Development
5.02
5.02
100%
B
RWSS Infrastructure Investments
196.78
103.40
53%
C
Program Management Support and M&E
22.09
11.60
52%

Total
224.00
120.00
54%


6.2 PROCESS FOLLOWED :

The following Project Cycle is followed to go through the cycle of detailed planning, implementation and O&M :

Project Cycle for Single Village Schemes:

Each scheme cycle includes four phases, including pre-planning (2 months),
planning (3-6 months), implementation (6-18 months), and operation and
maintenance phase (4 months). The duration of each phase depends on the
scheme size, technology type and the time it takes to mobilize the
communities.

(a) Pre-planning phase:

Major outputs of the pre-planning phase include:
(i) selection of support organization and (ii) collection of baseline data. Since GP is not a homogenous unit, most of the information is collected from each of the habitation of the GP to understand the access of different socio-economic groups to water and sanitation facilities and (iii) selection of GP/habitations

(b) Planning Phase: Following activities are under taken during Planning Phase:-(i) Mobilization of communities, participatory planning, and use of SARAR tools, problem investigation, analysis and solving. (ii) Formation of the User Water and Sanitation Committees (UWSSC). (iii) Selection of water supply & sanitation technology by the users in community wide meeting. (iv) Capacity building on community development, health, feasibility and design of water supply schemes, catchment area protection, accounting, etc. for SO/GP/UWSSCs members. (v) Preparation of detailed project reports and community action plan for each of the UWSSCs (vi) Collecting upfront cash and O&M community contribution for water supply, sanitation, and catchment area protection works. (vii) Involvement of women and marginal section of community in the whole planning phase.

(c) Implementation PhaseThe outputs of this phase include: (i) Preparation of Implementation Phase proposal, Construction of water supply schemes, environmental sanitation works and catchment area protection works by GP/UWSSC through community engineer contracted out by District Implementing Agency (DIA) (ii) Independent third party construction supervision by Service Agency (SA) and facilitation and monitoring by DIA, contracted out by SWSM. (iii) Collecting balance cash/labor and O&M community contribution for water supply, sanitation, and catchment area protection works (iv) Training on community development, health, women’s development initiatives, book keeping, O&M (technical, institutional, financial) etc. for GP/UWSSCs members. These activities are carried out by the SO of the planning phase and (v) Preparation of the Implementation Phase Completion Reports.

(d) Operation and Maintenance PhaseDIA provides technical assistance to the UWSSCs after commissioning of the water supply schemes to place the O&M system in order. Trainings at the GP/UWSSC level are conducted by DIA. The O&M system comprises the technical, financial, and the institutional systems. After establishing O&M system and completing all the activities stipulated in the agreement, the DIA formally exits from the GP. Thereafter the scheme maintenance continues to be carried out by the UWSSC.  However, the sector agencies continue to monitor and support the GPs on O&M issues, including large repairs, which cannot be undertaken at GP level.

6.2.1 Support Organizations and Service Agencies:

Non Governmental Organizations and Community based organizations are involved in the Sector Program as a link between the beneficiary communities and the district implementing agencies. Acting as catalysts in the process, they are involved in the scheme cycle activities in motivating and mobilizing the communities and building their capacities towards their envisaged roles and responsibilities in the management of their WATSAN schemes.

6.3  PROBLEMS ENCOUNTERED :

6.3.1 The challenges before the project were to develop a system, which embodies the philosophy of demand responsive approach, and provide an alternative to supply driven services delivery mechanism. The challenges before the implementing agency were to act as a facilitator and co financer (to provide assistance at appropriate time and ensure capital cost sharing by the community), as a monitor (the process and the progress) and as an agency to ensure the standards of construction, accounts and community development activities. The innovations and interventions at various levels are discussed in following paragraphs.
6.3.2 Appropriate change management efforts to shift the mindset of the sector institutions- from service provider to a facilitator were whole-heartedly taken up by engaging reputed training institutes. 
6.3.3 Steps had to be initiated for focusing on operations and maintenance aspects for sustainability of schemes in addition to the training programs on the design and implementation of RWSS schemes. How and where to interact with district level formal institutions had to be focused during capacity building in order to cover the eventualities of major repair works.
6.3.4 The Project Appraisal Document (PAD) and Operations Manual provide that the SWAp principles have to be followed for all new investments. It was recognized that in ‘exceptional situations’ the principles of ‘demand’ responsive community participation may not be practical. Examples of such exceptional situations include: damages due to natural calamities; damages due to road construction activities, water supply schemes for tourists en route pilgrimage sites; and emergencies like flood, drought, epidemics etc. The policy exceptions were sought from the World Bank.

7.  EVIDENCE OF PERFORMANCE:

7.1       The Sixth Implementation Support Mission April, 2010 of the World Bank in its Aide-Memoire has given the following project rating :-

India, Uttaranchal RWSS (Project ID:P083187; Loan/Credit No.:42320

 Key Project Data
Current Ratings and Flags
  Effectiveness Date
11/30/2006
Development Objectives
Satisfactory
  Closing Date
06/30/2012
Implementation Progress
Moderately Satisfactory
  Project Age
3.4 years
Problem Flags
None
 % Disbursed
            21

7.2  The Uttarakhand RWSS SWAp (first global RWSS SWAp) is being implemented following uniform policies and institutional arrangements across the State.  Schemes covering more than 1800 habitations have already laid a solid foundation for the SWAp program in Uttarakhand.
 
7.3 The decentralized institutional arrangements, processes and procedures are established and fully operational in all the 13 districts. The Gram Panchayat through the User Water Supply & Sanitation Committee (UWSSC) is fully responsible for Single Village Scheme (SVS) and intra-village Multi Village Scheme (MVS). The sector institutions are responsible for bulk water supply under the MVS. 


7.4 The water supply schemes are integrated with catchment area programs, household and village environmental sanitation programs, solid waste management and health and hygiene awareness promotion programs, in order to maximize water supply and health benefits to the communities.

7.5 Compared to the pre-project household coverage of sanitary latrines at 21%, the existing Project coverage has gone up to 71%, a difference of 50% achievement as a result of the Project efforts and the GoI Total Sanitation Campaign. The GoI Nirmal Gram Puruskar (NGP) award for clean villages has been received by 25% GPs (418 GPs) against the MTR target of 15% GPs.

7.6 While independent monitoring and social audits are in-built in the project design, the implementing agencies have started signing-off, providing quality assurance for the completed schemes. Also, continuous supervision has been introduced during the operations and maintenance stage to ensure technical and financial support to the Gram Panchayats (GPs). 
   
7.7 The district schedule of rates for various engineering items/ works/materials (local and non local) are jointly prepared by all the three implementing agencies based on the existing analysis of rates and are approved by the DWSM. This schedule of rates is updated on yearly basis or as and when needed. Thus there is a single set of schedule of rates for each district and for all the implementing agencies.

7.8  Culture of dependence on outsiders for a basic necessity like water is showing a diminishing trend leading to a positive indication of Gram Swarajya (Village Self Rule). In other words ‘community pride and community control’

7.9  Robust monitoring is followed to monitor processes, inputs, outputs and outcomes, including indicators of change under the project.     
7.10  Governance and accountability measures have been adopted as an integral part of the project design and implementation.  The Swajal Project Management Unit has consecutively received the Right to Information (RTI) award 2009&2010 for transparency and good governance practices, which include independent quality checks, community monitoring, grievance redressal measures, social audits, robust M&E and Sector-wide Information System (SIS), for information disclosure and tracking progress of the RWSS schemes in all phases of the project.   
8.   FACTORS OF SUCCESS:
 
8.1 Capacity building of all stakeholders: Capacity Building of all stakeholders was felt essential for effective and efficient implementation of the project. Therefore, a comprehensive capacity building plan was developed and include detailed and programmed training modules for: (i) SWSM and Program Management Unit (PMU); (ii) DWSMs and District Program Management Units (DPMUs); (iii) change management and community-development skills for sector institutions; (iv) general  training activities for PRIs; and (v) training of support organizations (SOs), and support agencies (SAs). Special training programs have been developed and implemented through the local training institutions to sensitize the state, district and village stakeholders and functionaries regarding the RWSS SWAp program. These programs include modules on planning and implementation of SVS and MVS, environmental and sanitation hygiene awareness programs and practices, financial and procurement management practices, etc. 

8.2 Information, Education, and Communications (IEC): The project has printed booklets, leaflets and posters that provide messages on the project, including health and hygiene, Total Sanitation Campaign, technology options for sanitation, use of toilets, good practice case studies, informal education, along with roles and responsibilities at the state, district and village levels. IEC activities, mainly to promote the decentralization agenda and SWAp program, have been carried out through workshops, cross-visits, competitions, IEC stalls, TV programs, etc. A couple of short documentary films have been prepared on the good practices currently being implemented under the project. 

8.3 Governance and Accountability Processes AdoptedIndependent reviews are an integral part of the project processes, including Concurrent Monitoring during the scheme planning phase, Third Party Construction Quality Checks, Technical Audits, Social Audits and Grievance Redressal Measures during the scheme implementation phase.  The Project clearly defines the roles and responsibilities of the beneficiary communities and community based organizations, NGOs, independent reviewers, PRIs, SWSM and the Implementing Agencies. 

8.4 PRI and Community Mobilization: Project has made a commendable effort in identifying, prioritizing and selecting GPs/villages/habitations for intervention. Subsequently, households in the selected habitations have been mobilized into a User Water Supply and Sanitation Committee (UWSSC), a sub-committee of the GP, which has proved to be an effective vehicle of community participation.  The SOs have contributed significantly towards mobilizing as well as capacitating the local communities. User surveys confirm full acceptance and satisfaction by the communities for water supply and sanitation schemes implemented under the project. Since it was recognized that the SOs would play the key role in achieving effective community participation, efforts were made to ensure that they would be selected and trained in an appropriate manner.

8.5 Social audit committee: This committee is constituted in each water supply scheme. The Social Audit Committee performs the following functions : (i) Ensure that all the committees follow Procurement Manual. (ii) Report any violation or deviation of rules to Gram Panchayat. (iii) Monitor the adherence of project principles and rules in selection of beneficiaries, implementation of sub projects and all decisions of UWSSC.

8.6 Grievance redressel mechanismThe Project provides for complete decentralization In the Pre Planning, Planning, Procurement, Construction & O & M of water supply schemes at grass root level where in decisions are taken by the concerned UWSSC with assistance of GP and facilitation by the SO and DIA. Grievance redressal at UWSSC Level : On receipt of a grievance the UWSSC convenes a community wide meeting and it is put up before the members of the UWSSC and the community. This process is facilitated by DIA and the representatives of the SO and the GP. It is note worthy to mention here that 146 out of total 154 grievances relating to various categories stand already attended to the satisfaction of the complainant since the inception of the project.

9 SUSTAINABILITY OF THE PROJECT: All steps are being taken during design, implementation and maintenance stages to ensure sustainability of schemes.  The project is currently on-going and a periodic review will be carried out to monitor sustainability. The project has designed a Sustainability Evaluation Exercise (SEE) to assess the sustainability of completed schemes which are more than one year old. Indian Institute of Public Administration has been engaged to conduct the independent study on sustainability perspectives. The study would be completed by March 2011.

10. REPLICABILITY OF THE PROJECT: This project has been a trend setter in the rural water supply and sanitation sector adopting sector wide approach. The Punjab project has been designed on the principles of the sector wide approach. The GoI’s rural water supply policies are also similar to policies and principles being followed in this project. Example : NRDWP.

11. LESSONS LEARNED:

11.1 The effective and efficient functioning of implementing agencies has reinforced the hypothesis, that proper orientation and training, a mix of skills, experience and gender can work in tandem to achieve positive results;
11.2 It has been proved that the partnership between village communities, NGOs and the government, where the government takes the role of facilitation and co-financing, has worked successfully;
11.3 The project has demonstrated that the communities can efficiently and effectively handle dispute resolutions, material procurement, financial transactions and record/ book keeping in a satisfactory manner, when properly trained;
11.4 Catchment Area Protection Works and water supply scheme construction works should be implemented simultaneously so that the sustainability of the tapped water source could be monitored during the project period itself;
11.5 The project has largely demonstrated that as long demand responsive approach is adopted, the communities are willing to contribute towards capital cost and plan implement, operate and maintain their own schemes;
11.6 The project has demonstrated that the alternative delivery system vis-à-vis the present top down government-dominated system is not only desirable but also feasible in the sector;
11.7 The capacity of the communities and the NGOs has been upgraded to such a degree that, the methodology of the project can be successfully carried over to other development areas;
11.8 A gender balance approach is important to ensure that both women and men have the same opportunities to influence and control the new services and share its benefits;
11.9 Observation Study Tour and Exposure visits have been found to be an effective tool in creating necessary awareness and in changing mindset of policy makers;
11.10 The possibility of misappropriating and misusing the funds is minimal if transparency at each stage is adhered to and monitored;
11.11 Irrespective of source of funding there should be uniform policy as regards to capital cost sharing as well as operation and maintenance. Otherwise the current systems are unsustainable.

12 ILLUSTRATIONS: attached

13 REFERENCES: Monthly Progress Reports, Third Party Construction Supervision Agency Reports, Concurrent Monitoring Reports, Mid-Term Evaluation Report, Aide-Memories, Project Appraisal Documents, Operations Manual, Financial Management Manual.

14 ATTRIBUTION: This case study is based on inputs given by the empowered village communities where the schemes have been completed or being implemented. Thanks to the empowered community for keeping the SWAp philosophy and program on the path to success!

15 AUTHOR: (i) Kapil Lall, Ex. Director, Project Management Unit, Uttarakhand Rural Water Supply & Sanitation Project, Dehradun.
                    



No comments:

Post a Comment